Minister: Tobacco Bay sewerage outfall system to be closed
A sewerage outfall at Tobacco Bay is set to close due to a major revamp of waste facilities in St George’s, Lieutenant-Colonel David Burch, the Minister of Public Works, told MPs yesterday.
Colonel Burch said the move was part of the ongoing $30 million East End Water and Wastewater Infrastructure initiative.
The minister told the House of Assembly the sewerage outfall system would be closed this year.
He said: “The project will enable a major environmental benefit for Bermuda.
“For the first time St George’s, inclusive of their hotels, will see all sewage redirected to Southside where it will be treated via a new wastewater treatment facility and no longer will there be a need to pump it overboard.
“This year we will be able to close the Tobacco Bay sewage outfall. This is a huge accomplishment that will contribute significantly to enhancing our marine environment.
“We have completed all main line trenching totalling approximately 17 miles of pipe. Note that each trench has three or four pipes.
“The only remaining works are the final connections to the new pump and lift stations.
“All remaining connections are being completed as the lift or pump stations are commissioned.”
The minister added that the provision of water and wastewater services in St George’s had experienced a number of challenges in the past.
Colonel Burch said that one of these was bathing water quality, stating: “Raw wastewater is pumped to the reef area northwest of St George’s Island and beach closures continue to occur.”
The minister said that $27 million of the project’s budget had already been used, and improving water services was a key goal.
He said: “This $30 million initiative is designed to enhance the lives of our citizens by rejuvenating old and creating new water systems that would properly treat sewage waste and provide potable – drinking – water to the parish of St George’s.
“Only a limited number of customers receive the services via public infrastructure.
“The remaining are self-served through their own private systems.”
The minister said that while the project had failed to meet its deadline of March 2023, it was expected to conclude “before the end of the summer”.
He added: “The primary reason for the delay is, yet again, the ongoing supply-chain and delivery issues for specialised equipment.
“Additionally, the other contributing factor was that this year has been very wet, especially over the last few months which made it difficult for contractors to complete equipment installations per the initial schedule.
“The work being done in the parish of St George’s will provide a much more reliable and quality of water to the people and businesses of the parish.
“It will also serve as a template for work that needs to be done in this area in other parts of the island.
“That infrastructure is also in need of repair and replacement.
“The lessons learnt through this exercise will provide a clear guide to improving the process as we move forward.”
Need to
Know
2. Please respect the use of this community forum and its users.
3. Any poster that insults, threatens or verbally abuses another member, uses defamatory language, or deliberately disrupts discussions will be banned.
4. Users who violate the Terms of Service or any commenting rules will be banned.
5. Please stay on topic. "Trolling" to incite emotional responses and disrupt conversations will be deleted.
6. To understand further what is and isn't allowed and the actions we may take, please read our Terms of Service